Objectives
Beak & Johnson commissioned TEG to project manage a fast-track project to relocate their soup manufacturing plant. The project scope included:
- 800m2 manufacturing area
- Process equipment
- HVAC & Services
- Boiler, steama nd condensate systems
- Refrigeration system
- Packing line
- Chilled storage
- Refurbished staff amenities and offices
- Total project value was $ 3.0m
Challenges
- Extremely tight timeframe
- Cost constraints
Results
Project successfully delivered a high standard facility delivered on time and under budget.